● There are strategies typically deal with threats or risks that may have negative impacts


● There are strategies typically deal with threats or risks that may have negative impacts on project objectives if they occur. Some other strategies are suggested to deal with risks with potentially positive impacts. (74) is a risk response strategy that may be adopted for either threats or opportunities.

(74) A. Share

B. Mitigate

C. Transfer

D. Acceptance

请帮忙给出正确答案和分析,谢谢!

参考答案
您可能感兴趣的试题
  • Project work packages are typically decomposed into smaller components called activities t

  • ● Project work packages are typically decomposed into smaller components called activities

  • ● Project work packages are typically decomposed into smaller components called activities

  • Many typically "American" characteristics are a result of value. 【M1】______ There is a re

  • ●Several risk response strategies are available.(75) the risk simply gives another party r

  • Only three strategies are available for controlling cancer prevention screening and trea