● The earned value technique is a commonly used method of performance measurement. It inte


● The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that __(74)__.

(74)A.the project is ahead of its planned schedule

B.less work was completed than was planned

C.the cost overrun for work completed

D.the cost under-run of performance to date

参考答案
您可能感兴趣的试题
  • ● The earned value technique is a commonly used method of performance measurement. It inte

  • The law of diminishing returns is manifested by the fact thatA.the elder generations earn

  • Which of the following topics is discussed during the interview?A.An electrician can earn

  • Which statement is not true about Pomodoro Technique?A.The Pomodoro Technique is a time

  • What is the criticism about Pomodoro Technique?A.The process is good at nothing.B.The p

  • The earned value technique is a commonly used method of performance measurement.It integr