In project management , a (1) is a listing of a project’s milestones, activities, and deli


In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.

A.schedule

B.activity

C.plan

D.contractor@@@SXB@@@A.finding

B.balance

C.allocation

D.distribution

请帮忙给出正确答案和分析,谢谢!

参考答案
您可能感兴趣的试题
  • In the project management context,(68)includes characteristics of unification, consolidati

  • ● Risk management allows the project manager and the project team not to(71). (71)A.elimin

  • ● In the project management context, (68) includes characteristics of unification, consoli

  • In project time management, activity definition is the process of identifying and document

  • Risk management allows the project manager and the project team not to(71). A.eliminate

  • ●Managing risk and documenting them is very important in project planning process. You are