On some projects, especially ones of smaller scope, activity sequencing, activity resource


On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and(70)are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.time estimating

B.cost estimating

C.project planning

D.schedule development

参考答案
您可能感兴趣的试题
  • On the one hand, it is indisputable that boarding schools are exerting a growing important effect, especially in last few years.(英译中)

  • ● On some projects, especially ones of smaller scope, activity sequencing, activity resour

  • Bob seems to have some problems in the current project.()

  • Should We Stop Celebrating Exotic Festivals? Some think Chinese, especially the young

  • Which one is not about learning opportunities?A.Cooperating on a project is an opportuni

  • An industrial society especially one as centralized and concentrated as that of Britain