● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a ne


● Project(71)is an uncertain event or condition that, if it occurs, has a positive or a negative effect on at least one project objective, such as time, cost, scope, or quality.

(71)

A.risk

B.problem

C.result

D.data

参考答案