● Project schedule management is made up of six management processes including: activity d


● Project schedule management is made up of six management processes including: activity definition, activity sequencing, (71) , and schedule control by order.

(71)

A.activity duration estimating, schedule developing, activity resource estimating

B . activity resource estimating, activity duration estimating, schedule development

C.schedule developing, activity resource estimating, activity duration estimating

D.activity resource estimating, schedule developing, activity duration estimating

参考答案
您可能感兴趣的试题
  • Developing the project schedule is often an iterative process. It determines the planned s

  • ●Developing the project schedule is often an iterative process. It determines the planned

  • Developing the project schedule is often an iterative process. It determines the planned s

  • ●Developing the project schedule is often an iterative process. It determines the planned

  • is a method used in Critical Path Methodology for constructing a project schedule ne

  • 28The reason that cost management is so difficult in project management is that: A.Project