● Creating WBS means subdividing the major project deliverables into smaller components un


● Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.

(75)

A.independent resource

B.individual work load

C.work milestone

D.work package

参考答案