问题

Many useful tools techniques are used in developing schedule. ()s a schedule network anal


Many useful tools techniques are used in developing schedule. ()s a schedule network analysis technique that modifies the project schedule to account for limited resource.

A.PERT B.Resource levelling C.Schedule compression D.Critical chain method

请帮忙给出正确答案和分析,谢谢!

参考答案