● (73)is the application of planned, systematic quality activities to ensure that the proj


● (73)is the application of planned, systematic quality activities to ensure that the project will employ all processes needed to meet requirements.

(73)

A. Quality assurance (QA)

B. Quality planning

C. Quality control (QC)

D. Quality costs

参考答案