● Schedule development can require the review and revision of duration estimates and resou


● Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress.

(74)

A.scope statement

B.activity list

C.project charter

D.project schedule

请帮忙给出正确答案和分析,谢谢!

参考答案